New Delhi: The government of India Wednesday launched Coking Coal Mission to meet the domestic demand. The Mission targets 140 million tonnes production of raw coking coal by 2030.

The details of domestic raw coking coal production and dispatch during 2020-2021 is as under:

(In Million Tonne)

SectorProductionDespatch
Public38.93438.150
Private5.8535.850
All India44.78744.000

The details of domestic raw coking coal dispatch of Coal India Limited (CIL) State-wise is as under:

(In Million Tonne)

StateDespatch in 2021-22Despatch in 2022-23(Till June)
Andhra Pradesh0.0040.000
Assam0.0270.024
Bihar5.7841.283
Chattisgarh0.1250.000
Delhi0.0010.027
Gujrat0.0040.000
Haryana2.6820.992
Jharkhand17.7775.375
Madhya Pradesh0.1510.026
Maharashtra0.0020.062
Punjab1.3230.729
Tamil Nadu0.1130.011
Uttar Pradesh5.1902.155
West Bengal14.5792.975
Nagaland0.0040.000
Grand Total47.76213.659

According to National Steel Policy 2017, to achieve steel making capacity of 300 MTPA (including 180 MTPA through Blast Furnace route) by 2030, ~170 MT coking coal will be required by 2030.

Government has launched Coking Coal Mission to meet the demand of domestic coking coal as projected by the Ministry of Steel and has set target for raw coking Coal production by 2030 as under-

CompanyProduction ( MT) by 2030
CIL105
Others including allocated coking Blocks35
Total140 MT