Bhubaneswar: Tata Power Renewable Energy Limited (TPREL) has successfully commissioned its 100 MW Group Captive Solar Project (TNGC-2) at Vellalankottai and Nalandhula villages in Kayathar, Tamil Nadu. With this commissioning, TPREL utility portfolio now grows to 12.3 GW and has surpassed the landmark 7 GW operational capacity milestone, reinforcing its position as a leading force in India’s clean energy transition.
The project will supply clean power to TP Solar Limited (40.625 MW), Tata Electronics Private Limited (53.125 MW), and Tata Realty And Infrastructure Limited (6.25 MW), reinforcing Tata Group Companies’ commitment to sustainable operations and accelerating India’s clean energy transition.
The project highlights TPREL’s expertise in executing large-scale solar projects through engineering excellence, best-in-class construction practices and a steadfast focus on quality.
The power generated will be transmitted through the Kayathar 400 kV Grid Substation (GSS), ensuring reliable evacuation and efficient delivery of renewable energy to the beneficiary companies.The Company’s 7 GW operational capacity comprise more than 5.7 GW of solar and 1.3 GW of wind energy assets.
Further strengthening its growth trajectory, TPREL has an additional 5.3 GW under various stages of development, including 2.2 GW of solar and 3.1 GW of wind projects, which are slated for phased commissioning over the next 6 to 24 months.
This project further reinforces TPREL’s position as a leader in India’s renewable energy transition and reflects its continued commitment to delivering innovative, high-quality renewable energy solutions that support the country’s target of achieving 500 GW of non-fossil fuel capacity by 2030.